Third Court Progress

Great News! Construction has begun on the third court.

February 17th, 2024

 

March 11th, 2024

Bocce Court 3 Addition Progress Week at April 1st.

Courts have been shot, blasted, ground and leveled. Courts 1-3 are ready to receive the new turf which is scheduled to be applied the week of April 15.

The shed/kiosk project will start on Monday, April 8 and the plan is to complete it by Friday, April 19th. Painting of the shed/kiosk will take place at a later date when all the trellis/railings are installed.

Landscape designs have been developed and are under review. The plan is to begin irrigation main line trenching next week.

The temporary fencing will be removed by Thursday April 18th.